The EH oil regeneration pump 2PB62DG28P1-V-VS40 plays a vital role in thermal power plants, and its normal operation is of great significance to the stability of the EH system. However, after the start-up trial run and a long period of shutdown, the oil in the pump body may be emptied, resulting in safety hazards during startup. This article will discuss how to correctly operate and install the EH oil regeneration pump in response to this problem.

EH oil regeneration pump 2PB62DG28P1-V-VS40 (1)

Start-up operation points of EH oil regeneration pump 2PB62DG28P1-V-VS40

1. Fill with oil: Before starting, the pump body needs to be filled with oil through the leaking oil pipeline. This is because when the pump is started, the system is in a pressure-free state, which is conducive to rapid oil filling and exhaust of the pump and pipeline.

2. Exhaust: At startup, a short-time switch is conducive to exhaust and can quickly fill the pump with oil. When the air in the pump body is emptied, the pressure naturally builds up.

3. Notes: During the startup process, closely observe the operation of the pump to ensure that there is no abnormal sound and vibration. Once a problem is found, the machine should be stopped and checked immediately.

EH oil regeneration pump 2PB62DG28P1-V-VS40 (3)

Installation method of EH oil regeneration pump 2PB62DG28P1-V-VS40

1. Horizontal installation: The pump should be installed horizontally to ensure smooth operation. The suction port and pressure port are located on the side to facilitate the connection of pipes.

2. Leakage port position: The leakage port should face upward or turn 90 degrees to ensure that it is always located as high as possible. This is to prevent oil leakage in the pump and affect the normal operation of the equipment.

3. Pressure port direction: The pressure port should face downward to avoid oil backflow.

4. Taboo: Never reverse the position of the leakage port and pressure port, otherwise it may cause equipment failure.

5. Vertical installation: If conditions limit, when vertical installation is required, the pump shaft should face upward to ensure the normal operation of the pump.

EH oil regeneration pump 2PB62DG28P1-V-VS40 (2)

The correct startup and installation of the EH oil regeneration pump 2PB62DG28P1-V-VS40 is of great significance to the safe production of power generation enterprises. By mastering the key points of startup operation and installation methods, the equipment failure rate can be effectively reduced and the power generation efficiency can be improved. In actual work, relevant personnel should strengthen the operation training and patrol inspection of the EH oil regeneration pump to ensure the safe and stable operation of the equipment.

In short, the correct operation and installation of the EH oil regeneration pump 2PB62DG28P1-V-VS40 is the key to ensure the normal operation of the EH system of the thermal power plant. Only by strictly abiding by the operating procedures can we create greater benefits for the enterprise.